North Kenilworth reliability improvement plan
We’re taking both immediate and long-term steps to improve the reliability of the underground electric system that serves the North Kenilworth neighborhood. Our goal is simple: Make your power service stronger, more dependable and better able to withstand future issues.
Immediate action: Quick response inspect and fix program
We have dedicated underground crews in the neighborhood right now, performing fast, proactive inspections and making repairs as soon as issues are identified. During the week of July 6, crews inspected about 80 transformers.
Each inspection includes:
- Preparing the work area safely (lifting lids, pumping water, and securing the site)
- Checking primary elbows for signs of wear
- Looking for corrosion, loose connections, overheating, or insulation concerns
- Inspecting the transformer housing to ensure the equipment is structurally sound
- Using infrared scanning to identify any hidden heat‑related issues
We have notified the New Orleans City Council that we will work directly with affected customers to coordinate any necessary outages.
Long-term improvements: Underground cable replacement
We are also accelerating a major project to upgrade the underground primary cable that serves the neighborhood. Construction is underway with employees and contractors from across the South.
This long-term project will:
- Replace older, direct‑burial cable with more durable, modern materials
- Add new conduit to better protect the system
- Reconnect the approximately 80 transformers to the new infrastructure once it’s installed
Some planned outages may be necessary during the final connection work. If that happens, customers and councilmembers will be notified directly — and in advance — and we’ll work to minimize disruption as much as possible.
Work has started and will be substantially complete by the end of August. We will continue to provide updates as work progresses.
A detailed action plan and schedule is shown below, and check back regularly for updates to this page.
North Kenilworth reliability action plan
Replacing aging underground cable reduces the risk of outages and provides customers with more reliable electric service
| Immediate action plan — Quick response inspection and repair program | Start date* | Status |
| Onboard contractor | July 6, 2026 | Complete |
| Thermal camera inspection of 80 transformers | July 7, 2026 | Complete |
| Identify issues and make repairs | July 7, 2026 | Complete |
| Long-term underground cable replacement plan — West side of Crowder Blvd. (See map above for referenced colors) |
||
| Yellow segment | July 2026 | Complete |
| Teal segment | Complete | |
| Orange segment | Complete | |
| Light purple segment | Complete | |
| Long-term underground cable replacement plan — East side of Crowder Blvd. (See map above for referenced colors) |
||
| Pink segment | July 2026 | Complete |
| Blue segment | Complete | |
| Dark purple segment | Complete | |
| Grey segment | Complete | |
| Light blue segment | Complete | |
| Brown segment | Complete | |